A premortem surfaces plausible failure mechanisms; it does not calculate probability or replace specialist controls.
All exercises
ChallengeExecuteLow
Premortem
Assume the plan failed and identify plausible mechanisms, indicators and countermeasures.
30–50 min6–16
Purpose
Reduce overconfidence and reveal failure knowledge before commitment.
Output: Prioritised risk register with indicators and owners
Materials
- Plan summary
- Failure cards
- Risk register
Preparation
- Choose a concrete plan with defined outcome and horizon.
- Clarify that the exercise does not replace formal risk or safety analysis.
Facilitation steps
1
Imagine failure
8 minState that the plan failed by the target date; write plausible reasons silently.
2
Cluster mechanisms
10 minGroup causes by mechanism without deleting minority risks.
3
Prioritise
10 minSelect risks by impact, plausibility and detectability.
4
Design control
12 minName an indicator, owner, prevention or response for each priority risk.
Observe
- Are uncomfortable risks softened?
- Do causes describe mechanisms rather than vague failure?
- Is an owner named?
Debrief
- Which risk changed the plan?
- What early signal would we monitor?
- What risk must be escalated outside this session?
Transfer to work
Add indicators and owners to the implementation plan and review them at the next checkpoint.
Failure modes
- The list is exhaustive but unprioritised.
- Participants treat imagined failure as evidence that failure is certain.
Accessibility
- Use silent written generation before speech.
- Provide a non-alarmist framing and clear boundaries.