Calculate and Recover a Data-Migration Schedule

Build the network, calculate the critical path and float, test resource feasibility and evaluate a controlled recovery scenario.

30 minutes

Scenario

A company must migrate customer data before a contractual platform shutdown. The plan lists dates but does not show dependency logic, float or the effect of a scarce integration engineer.

Your role
Programme scheduler validating the migration forecast
Method
Critical Path Method

Evidence pack

e1

A Mapping

Schema mapping takes 3 working days and starts the network.

e2

B Extraction

Extraction takes 4 days after mapping.

e3

C Interface

Interface build takes 6 days after mapping.

e4

D Cleansing

Cleansing takes 5 days after extraction.

e5

E–G

Integration test takes 3 days after interface and cleansing; UAT takes 4; cutover takes 1.

e6

Constraint

The integration engineer supports interface build and the first two days of integration test; no overlap is possible.

Constraints

  • Use working-day durations and state the date convention.
  • Do not remove validation or UAT.
  • Separate the contractual date from the calculated forecast.

Case steps

Work through each prompt using the evidence pack. These guided cases support self-directed practice; server-scored attempts are not available yet.

1
Structured

Create activity IDs, outputs, durations and predecessor logic and validate the network.

2
Structured

Perform forward/backward passes and identify critical and near-critical paths and float.

3
Open Response

Test the network against the scarce-engineer constraint.

4
Open Response

Cleansing slips two days. Evaluate schedule impact and one safe recovery option.